Boulder City ARPA Spending through 2022

City Hall Spring 2020

BOULDER CITY - The City of Boulder City received $21.7 million in American Rescue Plan Act (ARPA) funds in 2022. While $11.7 million must be spent on the COVID-19 public health emergency or its negative economic impacts, to provide grants to agencies that provide essential needs, for government services, or to make necessary investments in infrastructure (i.e. water, sewer), the remaining $10 million may be spent in any way under the streamlined revenue loss provision.  

In July, City Council approved a plan to invest the funds on a variety of projects, including infrastructure improvements as well as to help local organizations.  Here is a look at some of the larger expenditures as of December 31, 2022 (unaudited report):

PROJECT                                                                  BUDGETED                          SPENT        

 Water projects                                                            $6,413,006                         $1,755,601

Wastewater projects                                                   $3,906,531                          $180,137

Youth sports and pool fees                                          $175,000                             $175,000

EV vehicle pilot program                                             $350,000                             $349,632

City Clerk municipal code updates                             $500,000                              $165,107

Municipal Court unfunded mandates                         $300,000                              $272,202

Emergency Aid assistance                                        $100,000                               $38,680

See Spot Run requests                                              $50,000                                $50,000

Fire Department AED program                                   $50,000                                $49,407

Police Department tasers                                          $126,000                               $126,000

PD mobile field crowd control equipment                   $65,000                                $53,576

Spending in the months since City Council approved the budget totals more than $3.3 million. “I expect that the Fire Department substation, City facilities and security upgrades, and the Municipal Golf Irrigation projects will be addressed in the coming year,” said City Manager Taylour Tedder. “We have until the end of 2026 to spend the funds. City staff is doing its due diligence in planning out the projects and prioritizing those with the most significant impact first.”  

Visit www.bcnv.org/ARPA for updated reports and to view the entire budget plan.

Facebook Twitter Email

Other News in Boulder City News and Information

Joe Hardy Boulder City Mayor Headshot 2022-2

Proclamation for Peace

Posted on: October 18, 2023
Fire Prevention Week photo of Sparky

Fire Prevention Week is October 8-14

Posted on: October 5, 2023
City Hall Spring 2020

Job Fair Scheduled for October 18

Posted on: September 6, 2023
339699029.jpg

Power Outage

Posted on: September 8, 2023
power outage

Power Restored

Posted on: August 28, 2023
Leash cutting 8.2023

New Dog Park Open to the Public

Posted on: August 1, 2023
hilary

Stay Informed during Hurricane Hilary

Posted on: August 19, 2023
Boulder City website redesign

Boulder City Website Gets a Makeover

Posted on: July 18, 2023
power outage

Power Restored

Posted on: July 25, 2023
Community Resources Meeting Flyer - 5.18.2023

Community Resource Program Launches

Posted on: April 26, 2023
Zane Grothe

Zane Grothe Returns to BC!

Posted on: March 28, 2023
Easter Egg Hunt

Easter Egg Hunt Returns!

Posted on: March 16, 2023
big clean 2023

The Big Clean is March 25

Posted on: February 27, 2023
Helicopter Crash 12.27.22 WS

Hard Landing Sends Seven to Hospitals

Posted on: December 27, 2022
Alert

Fake 911 Call Leads to Short Lockdown

Posted on: December 7, 2022
Phone outage

Fire Department Phone Outage

Posted on: November 30, 2022